Projects registered by New Modern Buildwell Private Limited as promoter, as listed in the RERA registers of Maharashtra and Uttar Pradesh. Only granted registrations are shown. Every row links to the register for that project. Read from the register on 15 November 2026.
| Project | Location | Registration | Status | Register |
|---|---|---|---|---|
| NMBPL TOWER Commercial |
Lucknow, Uttar Pradesh |
UPRERAPRJ581302 Registered 26 Mar 2019 |
Registered Completion date in register: Dec 2025 |
Official page ↗ |
| NAVYUG PHASE-4 (NIRJHAR) Residential |
Prayagraj, Uttar Pradesh |
UPRERAPRJ739367 Registered 15 May 2019 |
Registered Completion date in register: Apr 2022 |
Official page ↗ |
| NAVYUG TOWER-15 (PHASE-3) Residential |
Prayagraj, Uttar Pradesh |
UPRERAPRJ17474 Registered 4 Sep 2018 |
Registered Completion date in register: Feb 2024 |
Official page ↗ |
| NAVYUG TOWER-EWS/LIG (PHASE-1) Residential |
Prayagraj, Uttar Pradesh |
UPRERAPRJ7118 Registered 5 Aug 2017 |
Registered Completion date in register: Mar 2027 Register notes a default on quarterly progress reports (QPR) |
Official page ↗ |
| T-12A (IRA) Residential With Vishwa Infrazone LLP |
Prayagraj, Uttar Pradesh |
UPRERAPRJ630123 Registered 26 Dec 2025 |
Registered Completion date in register: Feb 2027 Register notes a default on quarterly progress reports (QPR) |
Official page ↗ |
| U. S. Residency | Mawal Pune, Maharashtra |
P52100029751 | Registered | Official page ↗ |
On Legal Drive (legaldrive.in), which is run by Bitola Industries, the company that also runs Infratyke.
Looking for another project? Search all RERA-registered projects.
Source: Uttar Pradesh Real Estate Regulatory Authority and Maharashtra Real Estate Regulatory Authority. Infratyke has no relationship with this developer and shows only what the register states. Read the registration certificate, approvals and quarterly updates on the official page before you book, and see our guide on questions to ask a builder.