Search your state RERA authority's website for the project, then match the registered promoter, project name, phase and validity dates to your booking documents. Under Section 3(1) of the RERA Act 2016, no promoter may advertise, book or sell in a project that is not registered. Small projects of up to 500 sq m of land or eight apartments are exempt under Section 3(2)(a).

Key facts
Registration required beforeAny advertising, marketing, booking or sale (RERA Section 3(1))
ExemptionLand up to 500 sq m or up to eight apartments, all phases included (Section 3(2)(a))
Separate project account70% of buyer money, for construction and land cost only (Section 4(2)(l)(D))
Penalty for an unregistered projectUp to 10% of estimated project cost (Section 59(1))
Advance before agreementNot more than 10% of cost (Section 13(1))
In this article
  1. Which projects must be registered under RERA?
  2. How do you check a project's registration?
  3. What details should you match?
  4. What does the 70% account rule protect?
  5. What does registration not tell you?
  6. What are the red flags at booking?
  7. What can you do if the registration is missing or wrong?
  8. Frequently asked questions

A RERA registration number on a hoarding is easy to print. Checking that it belongs to the tower you are about to book, and that the details match your documents, takes ten minutes and is one of the most useful checks a buyer can make. This guide explains what to look for and why it matters.

Which projects must be registered under RERA?

Section 3(1) of the Real Estate (Regulation and Development) Act, 2016 says no promoter shall advertise, market, book, sell, offer for sale or invite people to buy any plot, apartment or building in a real estate project without first registering it with the state's Real Estate Regulatory Authority. Registration comes before the first advertisement, not after the first booking.

There is a size exemption. Under Section 3(2)(a), registration is not required where the land proposed to be developed does not exceed 500 square metres, or the number of apartments does not exceed eight, counting all phases. This is why some small builder-floor projects are outside RERA. Projects that were ongoing when the Act commenced, and had no completion certificate, had to apply for registration within three months under the proviso to Section 3(1).

How do you check a project's registration?

A project is registered with the RERA authority of the state where it is located, and authority websites do not all work the same way. Treat the steps below as a general method and follow the search options on your state's site:

  1. Get the registration number in writing from the builder or agent, along with the exact project and phase name as it appears in your allotment letter.
  2. Go to your state RERA authority's official website and search by registration number or project name. Use the official site, not a link sent on WhatsApp.
  3. Open the project record and read the details listed against it.
  4. Save a copy of the page and any documents you download, with the date. If something changes later, you have proof of what was shown when you booked.

Haryana's authority, for example, has benches at Panchkula and Gurugram, and Gurugram cases are decided by the Gurugram authority. If you are buying in Gurugram, Noida or Mumbai, check on that state's authority site.

What details should you match?

The registration has to fit your deal, not just the brand name. Compare these against your allotment letter, cost sheet and draft agreement:

CheckWhy it matters
Promoter's legal nameThe company you pay should be the registered promoter, not a sister company
Project and phase nameIf the project is built in phases, your tower must fall within what is registered
Registration validity dateCompare how long the registration runs with the possession date in your agreement
Sanctioned plan and layoutChanges need consent of two-thirds of allottees under Section 14(2)
Bank account for the projectYour payments should go to the account linked to the project

Not every website shows every item. Ask the promoter in writing for anything you cannot see, and if the details do not match, stop and get an explanation before paying more.

What does the 70% account rule protect?

Section 4(2)(l)(D) of RERA requires 70% of the money collected from buyers to be kept in a separate account in a scheduled bank, used only for construction and land cost. The promoter may withdraw only in proportion to completion, with each withdrawal certified by an engineer, an architect and a chartered accountant in practice, and the project accounts must be audited by a chartered accountant within six months of the end of every financial year.

This is why paying into the right account matters. Money sent to a different company or a personal account sits outside that protection.

What does registration not tell you?

Registration is not a guarantee that the project will be finished on time, or that its title is clean. It is a regulatory record. You still need to check title, approvals and the builder's track record. Our guide on verifying a property's title covers that.

Registration also does not reset your rights. In Imperia Structures v Anil Patni (2 November 2020), the agreed 42-month completion period had expired before the project was registered under RERA, and the builder argued the registration's validity date should apply. The Supreme Court held that for Section 18, the delay is measured from the agreement, not from registration.

What are the red flags at booking?

  • "Registration is coming next week." Booking before registration breaks Section 3(1). Under Section 59(1), the promoter faces a penalty of up to 10% of the project's estimated cost, and Section 59(2) adds imprisonment of up to three years or a further fine for not complying with orders.
  • A large advance without an agreement. Section 13(1) bars a promoter from taking more than 10% of the cost before a written agreement for sale.
  • An agent with no RERA details. Sections 9 and 10 of RERA deal with real estate agents, and Section 62 penalises an agent who contravenes them at Rs 10,000 a day, up to 5% of the unit's cost. Check the agent on your state authority's website. See how real estate agents work.
  • Brochure promises not on the record. Under Section 12, a buyer who pays based on a false statement in an advertisement, prospectus or model apartment can claim compensation, or withdraw with a full refund plus interest.

Our checklist of questions to ask a builder before booking and the guide to the allotment letter and builder-buyer agreement pick up from here.

What can you do if the registration is missing or wrong?

Section 31 of RERA lets any aggrieved person complain to the Authority or the adjudicating officer about any breach of the Act. Fees and forms vary by state. UP RERA takes complaints online in Form-M through the e-Court section of its portal, with a Rs 1,000 fee, as reported by Outlook Money on 10 May 2026. MahaRERA's fee for a direct complaint was Rs 5,000 under its Order No. 12 of 23 October 2019, and its conciliation forum charges Rs 1,000. Our step-by-step guide on how to file a RERA complaint and the page on home buyer rights under RERA explain the process and your refund rights.

If you have already paid a large sum, speak to a property lawyer early. You can find real estate advocates in Gurgaon and other cities on LegalFirms.

Frequently asked questions

Do builder floors need RERA registration?

It depends on size. Section 3(2)(a) of RERA exempts projects where the land does not exceed 500 square metres or the apartments do not exceed eight, counting all phases. A builder floor on a small plot often falls below these limits. If the project is larger, or the builder is selling several floors across connected plots, ask for the registration number.

Can I book a flat during a pre-launch before RERA registration?

Section 3(1) of RERA bars a promoter from advertising, marketing, booking or selling in a project that is not registered. A pre-launch booking in an unregistered project is therefore a booking the promoter should not be taking, and your money has less protection. Wait for registration and check it before paying anything.

What if the project's RERA validity date has passed?

The validity date reflects the timeline the promoter declared. If possession is late against your agreement, Section 18 lets you withdraw with a refund and interest, or stay and receive interest for each month of delay. The Supreme Court held in Newtech Promoters (2021) that the refund right is unconditional when possession is not given on time.

Does RERA registration mean the builder has all approvals?

Registration is a record with the regulator, not a certificate that every approval is in place or that the land title is clean. Check the sanctioned plans, title documents and approvals separately, and match them to the registration details. Section 18(2) of RERA does make the promoter liable to compensate buyers for loss caused by defective title.

Check the developer before you book: 39 developers with RERA-registered projects in Panchkula district and 522 developers with RERA-registered projects in Gurugram district, from the Haryana RERA register, with registration numbers and the official page for each project.

LegalFirms.in is run by Bitola Industries, which also runs Infratyke. We link to it where it helps with the step being described.

Sources

  • Real Estate (Regulation and Development) Act, 2016, Sections 3(1) and proviso, 3(2)(a), 4(2)(l)(D), 12, 13(1), 14(2), 18, 18(2), 31, 59(1), 59(2), 62 (India Code) India Code ↗
  • Supreme Court of India, Imperia Structures Ltd v Anil Patni, [2020] 12 SCR 373, 2 November 2020 Supreme Court of India ↗
  • Supreme Court of India, Newtech Promoters and Developers Pvt Ltd v State of UP, 2021 SCC OnLine SC 1044, para 25, as reproduced by the Haryana Real Estate Appellate Tribunal, 24 April 2026 Supreme Court of India ↗
  • Haryana Real Estate Appellate Tribunal, Appeal No. 321 of 2022, 30 November 2022, on HRERA Panchkula and Gurugram Haryana RERA ↗
  • Outlook Money, 10 May 2026, on UP RERA's online complaint system
  • MahaRERA Order No. 12, No. MahRERA/Secy/Order/1047/2019, 23 October 2019 MahaRERA ↗
Facts last reviewed on 06 Nov 2026. Laws, rates and schemes change; check the official source before you act. How we check facts
Found this useful? Pass it on
RB
Written by
Rishabh Bitola
Founder, Infratyke

Rishabh Bitola is the founder of Infratyke, the real estate lead marketplace operated by Bitola Industries Pvt Ltd, which connects people looking to buy, rent or sell property in India with local agents.

Published 11 Nov 2026 · Facts reviewed 6 Nov 2026 · Editorial policy
Free for buyers, tenants and owners
Looking for a property in Gurugram?

Tell us what you need in 20 seconds. Local agents who work in your area call you with options.

  • No more than 3 agents get your number
  • You pay Infratyke nothing
  • Spam-checked before release

Your number goes only to the agents who take your requirement. Add an email and we will tell you who they are. Privacy

We use cookies to improve your experience and analyse site usage. By continuing to use Infratyke, you agree to our privacy policy.