Home Buyer Rights Under RERA: What the Act Guarantees You
The Real Estate (Regulation and Development) Act, 2016 gives buyers in registered projects a written agreement before paying more than 10% of the price, carpet-area based sale, a protected 70% project account, possession on the agreed date or a refund with interest, free repair of defects reported within five years, and a registered conveyance deed. Complaints go to the state RERA Authority.
| Maximum advance before a written agreement | 10% of the cost (RERA section 13(1)) |
|---|---|
| Share of buyer payments kept in a separate project account | 70% (section 4(2)(l)(D)) |
| Defect liability after possession | Defects reported within 5 years, fixed free within 30 days (section 14(3)) |
| Projects exempt from registration | Land up to 500 sq m or up to 8 apartments (section 3(2)(a)) |
| Time to appeal a RERA order | 60 days to the Appellate Tribunal (section 44(2)) |
In this guide
- Which projects does RERA cover?
- What must the builder disclose, and how must the price be quoted?
- How does RERA protect the money you pay?
- Can the builder change the plan or cancel your allotment?
- What are your rights at possession and after?
- What if possession is late or the land title is defective?
- What does RERA expect from you as a buyer?
- What you can do if the builder breaks these rules
- Frequently asked questions
The Real Estate (Regulation and Development) Act, 2016 (Act No. 16 of 2016, enacted on 25 March 2016) places duties on builders, whom it calls promoters, and gives enforceable rights to buyers, whom it calls allottees. Below are the rights that matter most, the section that creates each one, and the time limits attached.
Which projects does RERA cover?
Under section 3(1), a promoter cannot advertise, market, book or sell any plot, apartment or building in a real estate project without first registering the project with the state's Real Estate Regulatory Authority. Projects that were already under way when the Act started, and had no completion certificate, had to apply for registration within three months.
Section 3(2)(a) exempts small projects: where the land does not exceed 500 square metres, or the project has no more than eight apartments across all phases. A builder floor on a single plot may fall outside RERA, and your protection then comes from your agreement, state apartment laws and consumer law.
A promoter who sells without registration faces a penalty of up to 10% of the estimated project cost under section 59(1). Before paying anything, search the project on your state RERA portal and match the registration number with the brochure. Our guide on checking RERA registration before you book shows what to look for, and it applies to any shortlist, including flats for sale in Noida.
What must the builder disclose, and how must the price be quoted?
Section 2(k) defines carpet area as the net usable floor area of the apartment. It excludes external walls, service shafts, exclusive balconies or verandahs and exclusive open terraces, but includes internal partition walls. Ask for the carpet area in writing and check that balcony and terrace areas are shown separately in the agreement.
Section 12 deals with misleading marketing. If you paid an advance on the strength of a false statement in an advertisement, brochure, prospectus or model apartment and suffered a loss, the promoter must compensate you. If you withdraw, the promoter must return your entire investment with interest at the prescribed rate plus compensation. Keep every brochure, email and message.
Section 13(1) limits what a promoter can collect before a written agreement for sale: no more than 10% of the cost of the apartment, plot or building as an advance or application fee. A demand for more without a signed agreement breaks the Act. Go through our allotment letter and builder-buyer agreement checklist before signing, and compare the builder's draft with a standard builder-buyer agreement format.
How does RERA protect the money you pay?
Section 4(2)(l)(D) requires the promoter to deposit 70% of the amounts collected from buyers in a separate account in a scheduled bank. That money may be used only for the construction and land cost of that project.
Withdrawals must be in proportion to the percentage of work completed, and each one must be certified by an engineer, an architect and a chartered accountant in practice. The project accounts must also be audited by a chartered accountant within six months after the end of every financial year. If work has stalled while large sums were collected, these certificates and audit reports are the first records a complaint should ask the Authority to examine.
Can the builder change the plan or cancel your allotment?
Under section 14(2), the promoter cannot alter or add to the sanctioned plans, layout plans, specifications or common areas without the prior written consent of at least two-thirds of the allottees, not counting the promoter. An extra tower on land shown as open space in the sanctioned layout, for example, needs that consent.
Section 11(5) says the promoter may cancel an allotment only in terms of the agreement for sale. If a cancellation does not follow the agreement, is unilateral, or is without sufficient cause, you can challenge it before the Authority.
What are your rights at possession and after?
| Right | Section | Time limit or detail |
|---|---|---|
| Completion or occupancy certificate | 11(4)(b) | Promoter must obtain it and make it available to buyers or their association |
| Association of allottees | 11(4)(e) | Within three months of a majority of units being booked, where local law is silent |
| Registered conveyance deed with share in common areas | 11(4)(f), 17(1) | Within three months of the occupancy certificate, where local law is silent |
| Handover of documents and plans | 17(2) | Within 30 days of the occupancy certificate, where local law is silent |
| Structural and workmanship defects | 14(3) | Reported within five years of possession, fixed free within 30 days |
| Outgoings until possession | 11(4)(g) | Promoter pays land cost, taxes, utility charges and mortgage dues until physical possession |
The defect clause is one of the most useful rights in the Act. Report each defect in writing, with photographs and a date, because the 30-day repair period runs from when it is brought to the promoter's notice. A dated room-by-room snag list made at handover is good evidence later.
Insist on the occupation certificate before you move in. In Samruddhi Co-operative Housing Society v Mumbai Mahalaxmi Construction (11 January 2022), the Supreme Court held that failure to obtain it is a deficiency in service, and noted that the society's members had been paying higher property tax and water charges as a result. The registered conveyance deed is the document that transfers the flat and your undivided share in the common areas to you, so press for it on the timeline above.
What if possession is late or the land title is defective?
Section 18(1) lets you withdraw and claim a refund with interest at the prescribed rate plus compensation if the promoter fails to give possession as per the agreement, or stops business because its registration is suspended or revoked. If you stay in the project, you are entitled to interest for every month of delay until possession. Our guide to delayed possession rights covers interest rates and court rulings in detail.
Section 18(2) separately requires the promoter to compensate buyers for loss caused by a defective title to the project land. Section 18(3) covers failure to meet any other obligation under the Act, the rules or the agreement.
What does RERA expect from you as a buyer?
Section 19 sets out your duties. You must pay instalments in the manner and time stated in the agreement (section 19(6)) and pay interest at the prescribed rate on late payments (section 19(7)). You must take physical possession within two months of the occupancy certificate (section 19(10)) and take part in registering the conveyance deed (section 19(11)).
The agreement cannot push every risk onto you, though. In Pioneer Urban Land v Govindan Raghavan (2 April 2019), the Supreme Court found an agreement wholly one-sided because it charged buyers 18% a year on late instalments but paid them only 9% for late possession, and held such clauses to be an unfair trade practice under the Consumer Protection Act, 1986.
What you can do if the builder breaks these rules
- Collect your papers. Allotment letter, agreement for sale, payment receipts, demand letters, brochures and correspondence. Note the completion date declared on the RERA portal.
- Write to the promoter. Send a dated notice by email and registered post naming the breach, the section and what you want: repair, a firm possession date or a refund.
- File a complaint under section 31. Any aggrieved person may complain to the Authority or the adjudicating officer. Following Newtech Promoters v State of UP (2021), refund and interest claims are decided by the Authority, while compensation under sections 12, 14, 18 and 19 is decided by the adjudicating officer, a serving or former District Judge appointed under section 71. Forms and fees vary by state; see how to file a RERA complaint.
- Consider the consumer route. Section 79 bars civil courts from matters RERA can decide, but in Imperia Structures v Anil Patni (2 November 2020) the Supreme Court held that consumer commissions are not civil courts and the buyer may choose either forum. Compare them in our guide to consumer commission cases.
- Appeal on time. An appeal to the Real Estate Appellate Tribunal must be filed within 60 days of receiving the order (section 44(2)). A promoter must first deposit at least 30% of the penalty to appeal (proviso to section 43(5)). A further appeal lies to the High Court within 60 days (section 58(1)).
This guide is general information on the RERA Act and the rulings named above, not legal advice. State RERA rules fix interest rates, forms and fees, so check your state's rules or speak to a real estate lawyer before you file.
Frequently asked questions
My project was registered under RERA after I signed the agreement. Which possession date counts?
The date in your agreement. In Imperia Structures v Anil Patni (2020), the agreed 42-month period had expired before the project was registered, and the Supreme Court held that the registration's later validity date did not postpone the buyers' rights. For section 18, delay is measured from the agreement, not from the RERA registration. The Court upheld a refund with 9% simple interest and costs of ₹50,000 per complainant.
Can a builder sell me a stilt parking space?
In Nahalchand Laloochand v Panchali Co-operative Housing Society (31 August 2010), decided under the Maharashtra Ownership Flats Act, 1963, the Supreme Court held that a stilt parking space is part of the common areas and is not sellable by the promoter. Its cost can be recovered only as a common area cost, shared in proportion to each flat's carpet area. Outside Maharashtra, check your state law and agreement.
My consumer case against the builder is already pending. Can I shift it to RERA?
The proviso to section 71(1) allows a complaint on matters under sections 12, 14, 18 and 19 that was pending before a consumer forum when RERA began to be withdrawn, with the forum's permission, and filed before the adjudicating officer. In Imperia Structures (2020) the Supreme Court said this is an option, not a compulsory transfer, so you can also continue in the consumer forum.
What can RERA do if the builder ignores its order?
Section 63 makes a promoter who fails to comply with an order or direction of the Authority liable to a penalty for every day of default, which can add up to 5% of the estimated project cost. Section 61 separately allows a penalty of up to 5% of the project cost for contravening other provisions of the Act. Keep a record of the order date and every missed deadline.
Check the developer before you book: 481 developers with RERA-registered projects in Gautam Buddha Nagar district and 3,322 developers with RERA-registered projects in Mumbai Suburban district, from the Maharashtra and Uttar Pradesh RERA registers, with registration numbers and the official page for each project.
Legal Drive and LegalFirms.in are run by Bitola Industries, which also runs Infratyke. We link to them where it helps with the step being described.
Sources
- Real Estate (Regulation and Development) Act, 2016 (Act No. 16 of 2016), sections 2(k), 3, 4(2)(l)(D), 11, 12, 13, 14, 17, 18, 19, 31, 43, 44, 58, 59, 61, 63, 71, 79, India Code India Code ↗
- Supreme Court, Newtech Promoters and Developers Pvt Ltd v State of UP, 2021 SCC OnLine SC 1044 (paras 25 and 86 as reproduced by the Haryana Real Estate Appellate Tribunal) Supreme Court of India ↗
- Supreme Court, Imperia Structures Ltd v Anil Patni, Civil Appeal Nos. 3581-3590 of 2020, 2 November 2020, [2020] 12 SCR 373 Supreme Court of India ↗
- Supreme Court, Pioneer Urban Land and Infrastructure Ltd v Govindan Raghavan, Civil Appeal No. 12238 of 2018, 2 April 2019 Supreme Court of India ↗
- Supreme Court, Samruddhi Co-operative Housing Society Ltd v Mumbai Mahalaxmi Construction Pvt Ltd, Civil Appeal No. 4000 of 2019, 11 January 2022 Supreme Court of India ↗
- Supreme Court, Nahalchand Laloochand Pvt Ltd v Panchali Co-operative Housing Society Ltd, Civil Appeal No. 2544 of 2010, 31 August 2010 Supreme Court of India ↗
Rishabh Bitola is the founder of Infratyke, the real estate lead marketplace operated by Bitola Industries Pvt Ltd, which connects people looking to buy, rent or sell property in India with local agents.