Snag List
A snag list is a written list of defects, incomplete work and faults found when inspecting a new flat or house before or at possession, given to the builder to fix.
A snag is anything that does not match what was promised or does not work properly: seepage, cracks, hollow or uneven tiles, doors that do not shut, faulty wiring, missing fittings, or a specification different from the agreement. A snag list records each one with its location, a photograph and a date, so there is no argument later about what was reported and when.
Your legal backing
Section 14(3) of the Real Estate (Regulation and Development) Act, 2016 says that if any structural defect or any other defect in workmanship, quality or provision of services is brought to the promoter's notice within five years from the date of handing over possession, the promoter must rectify it without further charge within thirty days. A dated snag list sent to the builder is the simplest proof of notice. If the builder does not act, section 31 lets you complain to the state RERA authority; see how to file a RERA complaint.
Section 14(2) also bars the promoter from altering the sanctioned plans, layout plans and specifications without the written consent of at least two-thirds of the allottees. If your flat differs from the agreed specification, put it on the list.
How to make a useful snag list
- Inspect in daylight, then again after running every tap, flush and switch.
- Go room by room; our room-by-room snag checklist covers what to test.
- Number each item, attach photos and send the list by email or letter so the date is on record.
- Re-inspect when the builder says the work is done, and close items only when you are satisfied.
Common mistake
Signing for possession first and listing snags later from memory. Prepare the list before you sign the possession certificate, and keep a copy of everything you send.
- Real Estate (Regulation and Development) Act, 2016, sections 14(2), 14(3) and 31 India Code ↗