Delayed Possession: Your Rights to Refund, Interest and Compensation
If a builder misses the possession date in your agreement, section 18 of the RERA Act, 2016 lets you either withdraw and get your money back with interest and compensation, or stay in the project and receive interest for every month of delay until possession. The Supreme Court has called the refund right unconditional. A consumer commission is an alternative forum for the same grievance.
| Refund on delay | Amount paid plus prescribed interest and compensation (RERA section 18(1)) |
|---|---|
| If you stay in the project | Interest for every month of delay till possession (proviso to section 18(1)) |
| Haryana interest formula | SBI highest MCLR plus 2% (Rule 15, Haryana RERA Rules, 2017) |
| Consumer complaint time limit | 2 years from the cause of action, delay can be condoned (CPA 2019, section 69) |
| District Commission limit | Consideration paid up to ₹50 lakh (Jurisdiction Rules, 30 December 2021) |
In this guide
- When does a delay legally begin?
- What are your two options under section 18?
- How is the interest rate worked out?
- Is the compensation clause in your agreement binding?
- RERA or consumer commission: which should you choose?
- Does taking possession or the conveyance deed end your claim?
- What about stalled projects in Noida and Greater Noida?
- What you can do now
- Frequently asked questions
When a builder misses the promised date, the law gives you more than a polite apology letter. This guide covers when a delay starts, the two choices you have, how interest is worked out, and how to pick between RERA and a consumer commission.
When does a delay legally begin?
The clock runs from the possession date in your agreement for sale. In Imperia Structures v Anil Patni (2 November 2020), the agreement promised completion in 42 months and that period ended before the project was registered under RERA. The builder argued that its registration was valid till 31 December 2020. The Supreme Court held that the buyers' rights under section 18 are measured from the agreement, not from the RERA registration, and upheld a refund with 9% simple interest and ₹50,000 costs per complainant.
Grace periods do not stretch forever either. In Pioneer Urban Land v Govindan Raghavan (2 April 2019), the Court held that a buyer cannot be forced to accept possession offered about two years after the grace period expired, and is entitled to a refund with compensation. It relied on Fortune Infrastructure v Trevor D'Lima, (2018) 5 SCC 442, which holds that a buyer cannot be made to wait indefinitely.
What are your two options under section 18?
| Your choice | What the promoter must pay | Who decides |
|---|---|---|
| Withdraw from the project | Full amount received, with interest at the prescribed rate, including compensation (section 18(1); also section 19(4)) | RERA Authority for refund and interest; adjudicating officer for compensation |
| Stay in the project | Interest at the prescribed rate for every month of delay until possession (proviso to section 18(1)) | RERA Authority |
The split in the last column comes from Newtech Promoters v State of UP (2021). The Supreme Court said that for refund, interest on the refund, or interest for delayed possession, the regulatory Authority decides; compensation under sections 12, 14, 18 and 19 is exclusively for the adjudicating officer. Applying that, the Haryana Real Estate Appellate Tribunal, in an order of 16 March 2022, set aside a refund ordered by an adjudicating officer as being without jurisdiction. Filing in the wrong forum can cost you months.
Newtech also described the refund on demand as "an unconditional absolute right to the allottee" if possession is not given within the agreed time. Section 18 adds that this is "without prejudice to any other remedy available", which keeps other forums open.
How is the interest rate worked out?
RERA leaves the rate to each state's rules. In Haryana, Rule 15 of the Haryana Real Estate (Regulation and Development) Rules, 2017 pegs it to the State Bank of India's highest marginal cost of lending rate (MCLR) plus two per cent. An HRERA Panchkula order of 7 December 2022, for instance, applied 8.35% plus 2%, which is 10.35% a year, and the Haryana Real Estate Appellate Tribunal found "no infirmity" in that formula on 5 June 2025.
Because the rate floats with SBI's MCLR, the figure in each order depends on the MCLR on the order date, so nobody can quote you one fixed current rate. If you are outside Haryana, read your own state's RERA rules for the prescribed rate before you calculate a claim.
Courts have also refused to let builders cap the rate at what the agreement offered. In Pioneer Urban Land (2019), the Supreme Court upheld 10.7% simple interest and rejected the builder's plea to limit it to the agreement's 6% or 9%. In Rajnesh Sharma v Business Park Town Planners (24 September 2025), it raised the National Commission's 9% interest on a refund to 18% a year, the rate the builder had charged the buyer for late payments, while noting that the builder's rate is not automatically the buyer's rate.
Is the compensation clause in your agreement binding?
Often not. In Wg Cdr Arifur Rahman Khan v DLF Southern Homes (24 August 2020), the Supreme Court held that failure to deliver within the contractual period is a deficiency of service, and that consumer fora are not bound by a nominal clause of ₹5 per sq ft per month. They may award just and reasonable compensation instead.
Under section 72 of RERA, the adjudicating officer weighs the disproportionate gain or unfair advantage the builder made, the loss you suffered, and whether the default is repeated. Collect proof of your actual loss, such as rent paid while waiting and pre-EMI interest on your home loan, because it supports a higher award.
RERA or consumer commission: which should you choose?
Section 79 of RERA bars civil courts from matters RERA can decide. In Imperia Structures the Supreme Court held that a consumer commission is not a civil court, so a buyer has a choice of forum. The Consumer Protection Act, 2019 expressly lists "housing construction" as a service in section 2(42).
| Point | State RERA | Consumer commission |
|---|---|---|
| Which body | Authority for refund and interest; adjudicating officer for compensation | District, State or National Commission, depending on the consideration paid |
| Value limits | None | District up to ₹50 lakh; State above ₹50 lakh to ₹2 crore; National above ₹2 crore (2021 Rules) |
| Time limit to file | Not set in the sections covered here | Two years from the cause of action, extendable for sufficient cause (section 69) |
| Target disposal | Not set in the sections covered here | Three months where no testing is needed (section 38(7)) |
| First appeal | Appellate Tribunal within 60 days (section 44(2)) | Within 45 days to the State Commission, with 50% of the amount deposited (section 41) |
Consumer jurisdiction depends on the amount you actually paid for the flat, not the total price or the compensation you claim. District Commission fees after the December 2022 amendment are nil up to ₹5 lakh, ₹200 up to ₹10 lakh, ₹400 up to ₹20 lakh and ₹1,000 up to ₹50 lakh. You can file where you live or work (section 34(2)(d)), and electronic filing is allowed.
Does taking possession or the conveyance deed end your claim?
No. In Arifur Rahman Khan (2020) the Supreme Court held that signing conveyance deeds does not bar flat buyers from claiming compensation for delay. If you stay in the project and the occupancy certificate is issued, section 19(10) still requires you to take possession within two months, so take it and record in writing that your delay claim is reserved.
Inspect the flat before you sign the possession letter, using a snag checklist, and confirm the occupation certificate has been issued.
What about stalled projects in Noida and Greater Noida?
A committee chaired by Amitabh Kant reported on stalled projects on 21 August 2023, citing about 2.4 lakh stressed homes in NCR. The UP cabinet accepted its recommendations on 19 December 2023: a zero period from 1 April 2020 to 31 March 2022, registries once developers pay 25% of their dues to the authority, and completion within three years. As of June 2024, Noida Authority reported registering about 1,075 flats in 22 stalled projects under this package.
The package deals with dues between developers and the authorities and registration of flats. Your own claim against the builder is a separate matter under RERA or consumer law. Read our guide on Noida's leasehold and authority rules, and check completion status before you consider flats in Greater Noida.
What you can do now
- Fix your dates. Note the possession date and any grace period in the builder-buyer agreement, and the date of each payment.
- Total what you paid. Add every receipt. This figure decides the consumer forum and is the base for refund and interest.
- Decide: refund or interest. Withdraw if you have lost faith in completion; stay if the project is near completion and you still want the flat.
- Send a written demand. Cite section 18, state your choice and give a deadline.
- File in the right forum. Refund or interest to the RERA Authority, compensation to the adjudicating officer, or the whole claim before a consumer commission. See how to file a RERA complaint and consumer commission cases.
- Track appeals. If the builder appeals a RERA order, it must first deposit at least 30% of the penalty (section 43(5)); in consumer appeals the appellant deposits 50% of the amount ordered.
For the full list of buyer protections beyond delay, see home buyer rights under RERA. This page is general information, not legal advice. Interest rules and procedures differ by state, so speak to a consumer protection lawyer before you file.
Frequently asked questions
Can the builder refuse a refund because of Covid, a court stay or approvals delay?
The Supreme Court in Newtech Promoters (2021) said the refund right applies if possession is not given within the agreed time "regardless of unforeseen events or stay orders of the Court/Tribunal" which are not attributable to the buyer. It added that the right is not dependent on any contingencies or stipulations. A builder can argue its case, but the starting point favours the buyer.
I bought my under-construction flat from the original buyer. Can I claim delay compensation?
Be careful here. In Arifur Rahman Khan v DLF Southern Homes (2020), the Supreme Court excluded subsequent transferees and buyers who had signed voluntary settlements from the delay compensation it awarded. Your position depends on the transfer documents, the date you came in and what the builder endorsed. Take advice on your specific papers before filing.
My delay began more than two years ago. Is a consumer complaint time-barred?
Not necessarily. Section 69 of the Consumer Protection Act, 2019 allows a late complaint if you show sufficient cause. In Pushpa Jagannath Shetty v Sahaj Ankur Realtors (28 February 2025), the Supreme Court treated ongoing letters, meetings and escrow communications as a continuing cause of action. In Samruddhi (2022), failure to obtain an occupation certificate was held to be a continuing wrong.
Can I claim both interest and compensation?
Yes. Section 18(1) provides for return of the amount with interest "including compensation", and section 18(3) covers compensation for other breaches. Under Newtech, the RERA Authority decides refund and interest, while compensation and interest on it are decided by the adjudicating officer. So you may need to approach both within your state RERA.
Check the developer before you book: 39 developers with RERA-registered projects in Panchkula district and 481 developers with RERA-registered projects in Gautam Buddha Nagar district, from the Haryana and Uttar Pradesh RERA registers, with registration numbers and the official page for each project.
LegalFirms.in is run by Bitola Industries, which also runs Infratyke. We link to it where it helps with the step being described.
Sources
- Real Estate (Regulation and Development) Act, 2016, sections 18, 19, 43(5), 44(2), 71, 72, 79, India Code India Code ↗
- Haryana Real Estate (Regulation and Development) Rules, 2017, Rule 15; Haryana Real Estate Appellate Tribunal orders of 16 March 2022 (Appeal No. 75 of 2021) and 5 June 2025 (Appeal No. 534 of 2024) Haryana RERA ↗
- Supreme Court, Newtech Promoters and Developers Pvt Ltd v State of UP, 2021 SCC OnLine SC 1044 Supreme Court of India ↗
- Supreme Court, Imperia Structures Ltd v Anil Patni, 2 November 2020, [2020] 12 SCR 373 Supreme Court of India ↗
- Supreme Court, Pioneer Urban Land and Infrastructure Ltd v Govindan Raghavan, 2 April 2019 Supreme Court of India ↗
- Supreme Court, Wg Cdr Arifur Rahman Khan v DLF Southern Homes Pvt Ltd, 24 August 2020, [2020] 9 SCR 136 Supreme Court of India ↗
- Supreme Court, Rajnesh Sharma v Business Park Town Planners Ltd, 24 September 2025 (as reported by ThePrint, 26 September 2025) Supreme Court of India ↗
- Supreme Court, Pushpa Jagannath Shetty v Sahaj Ankur Realtors, 2025 INSC 294, 28 February 2025 Supreme Court of India ↗
- Supreme Court, Samruddhi Co-operative Housing Society v Mumbai Mahalaxmi Construction, 11 January 2022 Supreme Court of India ↗
- Consumer Protection Act, 2019, sections 2(42), 34, 35, 38, 41, 69; Consumer Protection (Jurisdiction) Rules, 2021, G.S.R. 912(E), 30 December 2021; amended rule 7 fee slabs (December 2022, as reported by DT Next) India Code ↗
- Amitabh Kant committee report, 21 August 2023, and UP cabinet decision of 19 December 2023 (as reported by ThePrint, Swarajya and Millennium Post)
Rishabh Bitola is the founder of Infratyke, the real estate lead marketplace operated by Bitola Industries Pvt Ltd, which connects people looking to buy, rent or sell property in India with local agents.